a motorcycle company produces 3 models. I need 54 of #1, 42 of #2, 30 of #3 in...

DarleneP

New member
Joined
Feb 9, 2009
Messages
1
Reaction score
0
Points
1
...a 7 hr shift. how long per bike? The average time per cycle required to complete the order in a 7 hr. shift.
 
54+42+20 divided by 7 gives you the per hour rate.

16.5/hr roughly.

60 mins/hr divided by 16.5 gives how many minutes per bike.

3.63
 