Working alone, it takes Joe 11 hours to tar a roof?

YOUWANTME

New member
Working alone, it takes Joe 11 hours to tar a roof. Mark can tar the same roof in 12 hours. If they worked together how long would it take them?

I need to know how to do it so can you explain or point me to a helpful site?
 

I'mwithStupid

New member
Joe tars at the rate of 1/11 roofs per hour
Mark tars at the rate of 1/12 roofs per hour
so
together they tar at (1/11 + 1/12) roofs per hour
or, simplified: 23/132 roofs per hour.
so it would take them:
132/23 hours per roof
or about 5.74 hours

??
 